13 February 2012
Start a new Otto Junker induction furnace plant with a production capacity of 7 ton hours.
The new furnace plant consist of two 6 ton furnaces with one common IGBT converter with a power of 4,0000 kw. The furnaces plant is controlled by Otto Junker interface M2F of the latest generation This plant facility allows us to have a lot of flexibility on the production quantity and quality.
New installation system of molding sand and resin with IMF fast loop system.
Isle of vibration forms.
Paint system of forms and drying in the oven with mechanized movements.
This system, in addition to increasing the degree of efficiency and response, considerably increases the aesthetic quality of our products.
September 6, 2010
Fima Olimpia will participate to GLASSTEC 2010, that will take place in Dusseldorf from September 28 to October 1. Stand 13 A11.
September 4, 2010
We have started the process for obtaining the Health and Safety Management System OHSAS 18001:2007 certification; we anticipate obtaining it in late 2010 or in the spring of 2011.
July 20, 2010
Once again, Fima Olimpia will participate in this year’s edition of GLASSTEC, an International Trade Fair for the Glass Industry that will take place in Dusseldorf from September 28 to October 1.
June 30, 2010
Raw materials: the price increases have stopped. The Extra MP rate applied during May and June is confirmed for July.